By Lauren Krugel A project to increase the amount of crude that can flow on the Trans Mountain Pipeline using chemical additives has been completed two months ahead of schedule, the Crown corporation said as it released third-quarter results on Friday. The drag-reducing agent increases the pipeline’s capacity by up to about 10 per cent to 980,000 barrels per day. Trans Mountain carries oil from the Edmonton area to Burnaby, B.C. A further expansion of 210,000 barrels per day, using new pipeline segments and pump stations, is expected to come into service by the end of 2028, bringing the system’s total capacity to 1.19 billion barrels a day. At least 17 First Nations in Alberta and B.C., one U.S. tribe in Washington state and one individual have filed legal challenges…