Hamilton changes site trucking waste stop after MOE says no

By Lisa Iesse Writer HAMILTON – Ontario’s ministry of environment has pulled the brakes on 8,000 cubic metres or 16,000 tons of Chedoke Creek waste enroute to a local suburban landfill site in Hamilton. About one month ago, in a message posted on their website the city announced the clean-up was complete. “The in-water targeted dredging activities are completed, concluding the four-month effort to remove sediment from the bottom of Chedoke Creek.” It was a job that came with a $10.4 million price tag. “We’re running around 32 trucks a day of dried material as we’re able to,” Nick Winters, the city’s director of water told city council on November 21. About 2 weeks ago, the province stepped in warning that the planned dumping site, the GFL landfill in Stoney…

This content is for Yearly Subscription, Yearly Subscription – Corporate, and Print Subscription Only members only.
Log In Register

Add Your Voice

Is there more to this story? We'd like to hear from you about this or any other stories you think we should know about. Contribute your voice on our contribute page.