By Carl Clutchey, Local Journalism Initiative reporter A proposed multimillion-dollar upgrade to Ontario Power Generation’s Kakabeka Falls generating station is being planned without Fort William First Nation’s input, recalling an outdated and painful era that left Indigenous people being “bulldozed,” the community warned on Friday. “The existing hydroelectric facility was originally developed over 120 years ago without consultation with the Nation, and resulted in flooding, changes to waterways, and irreparable damages to Fort William First Nation’s cultural heritage and ways of life,” the community said in a news release. Work on the 118-year-old station is anticipated to begin next year. The project is expected to take two years, bumping up the power station’s output by 13 per cent to 27 megawatts. Once the upgrade is complete, the station — which is…